Design and budget for national highway G360 Wenchang to Ding’an and Ding’an to Lingao approved

The Preliminary design and budget for the national highway G360 Wenchang to Ding’an section and Ding’an to Lingao section have been approved.

The estimated total investment is about 11.5 billion yuan

Haikou, September 3rd, The preliminary design and budget estimates for the national highway G360, Wenchang to Ding’an section and Ding’an to Lingao section were approved.

The total investment of the two roads is about 11.5 billion yuan.   

In August 2019, the Provincial Development and Reform Commission approved the preliminary design and budget estimates for the national road G360 Ding’an to Lingao section. 

The project route is 80.218 kilometers long. The whole section will use asphalt and concrete pavement, adopting a two-way, four-lane highway, with first-class standards, and a design speed of 100 km/h. 

The total estimated budget of the project is approximately RMB 7.732 billion.

The Provincial Development and Reform Commission also approved the preliminary design and budget estimates for the National Highway G360 Wenchang to Ding’an section. 

The project route is 41.63 kilometers long and will also have a design speed of 100 km/h. The total estimated budget of the project is approximately 3.763 billion yuan.

The national highway G360 Wenchang to Ding’an section, Ding’an to Lingao section of the highway is seen as an important national road connecting northern and western Hainan

The construction project is seen as being of great significance to improving the investment environment of cities and counties along the route, accelerating the development and utilization of resources and implementing the “Third Five-Year Plan” for poverty alleviation on the island.